« home

 

ENVIRONMENTAL REVIEW

 
Project Description
Corridor Alternatives
Environmental Review
Funding
Public Outreach
Project Schedule
Project Library
Who to Contact
   
   
   
   
   
   
   
   
   


 

    Phase 1 of the Placer Parkway Corridor Preservation Project is to identify a reasonable range of alternatives. These corridor alignment alternatives (see CORRIDOR ALTERNATIVES) will be analyzed in Phase 2 – the Tier 1 Environmental Impact Statement/Environmental Impact Report (Tier 1 EIS/EIR).

Tiering
Plans for large infrastructure projects, such as the Placer Parkway, are developed over many years. Generally, greater detail becomes available as the planning process moves forward. To make sure that environmental analysis is included and considered as early in the process as feasible, federal and State environmental laws allow for a tiered environmental review. “Tiering” is a streamlining concept for large infrastructure projects with several stages or phases. It is a way to focus environmental studies during the planning process at the same level of detail as the plans.

Description of "Tiering"

Tier 1 EIS/EIR
This environmental document will address federal (National Environment Policy Act – NEPA) and State (California Environmental Quality Act – CEQA) requirements for the Placer Parkway Corridor Preservation Project. It will evaluate the corridor alternatives and will lead to the selection of one corridor for right-of-way preservation.

The Federal Highway Administration (FHWA), the California Department of Transportation (Caltrans), and the South Placer Regional Transportation Authority (SPRTA) propose to select and preserve a corridor for the future construction of the Placer Parkway.  FHWA is the NEPA lead agency.  SPRTA is the CEQA lead agency.  SPRTA has authorized Placer County Transportation Planning Agency (PCTPA) to carry out the work.

Environmental Process
The following steps are being taken to complete the Placer Parkway Corridor Preservation Tier 1 EIS/EIR:

  1. Scoping
    The scoping process solicits input from the public and agencies regarding the extent and significant environmental issues to be addressed in the environmental document. The Notice of Intent (NOI), to address NEPA provisions, was published in the Federal Register on September 18, 2003. The Notice of Preparation (NOP), to address CEQA provisions, was sent to the State Clearinghouse on September 22, 2003 as well as to interested agencies, organization, and individuals. These notices serve as the official legal notice that the Tier 1 EIS/EIR is to be prepared.

    As part of the scoping process, two public scoping meetings were held. The first, on October 6, 2003, was in Roseville. The second was held in Pleasant Grove on October 9, 2003. For background and recap, see PUBLIC OUTREACH.
     
  2. Draft Tier 1 EIS/EIR
    It evaluates the corridor alternatives, identified by the SPRTA Board in September 2005. It will lead to the selection of one corridor for right-of-way preservation. The Tier 1 EIS/EIR emphasizes the relative differences among the corridor alternatives regarding potential impacts. This information will allow for an informed choice among the alternatives. The Tier 1 EIS/EIR  focuses on broad topics such as general location, mode choice, and area-wide air quality and land use, along with other environmental issues. It also identifies mitigation strategies to be used in later design/construction (Tier 2) environmental reviews.

    The Draft Tier 1 EIR/EIS was released for public review and comment on July 2, 2007.  Public hearings were held in Yuba City on August 6, 2007 and in Roseville on August 8, 2007 to get comments on the Draft.  The extended comment period closed on September 25, 2007.

    The following technical reports/studies are the basis of the Draft Tier 1 EIS/EIR:
     

    Access & Buffer Chapter and Re-Circulation
    Because of re-emerging questions about the access/buffer provisions and to address USEPA comments on the Draft Tier 1 EIS/EIR, the SPRTA Board conducted a public workshop on February 27, 2008. The Board considered a number of options. On March 26, 2008, the Board directed the staff to prepare a Draft Tier 1 EIS/EIR chapter containing the additional analysis for growth inducement, secondary/indirect impacts, and cumulative impacts as well as considering a hypothetical scenario including less buffers and more interchanges. The new chapter is to be circulated for public review.

    This effort is to provide fuller, more formal public disclosure of the additional work and to make a better foundation for later Tier 2 work.
     

  3. Final Tier 1 EIS/EIR
    After the Draft Tier 1 EIS/EIR public comment period ends, the Final Tier 1 EIS/EIR will be prepared. Among its required components, the Final Tier 1 EIS/EIR must respond to the comments received on the Draft Tier 1 EIS/EIR.

    After the Final Tier 1 EIS/EIR is prepared and before action can be taken on the project, several decision-making documents are required. These include the Record of Decision (NEPA) by FHWA and the Notice of Determination, Notice of Availability, Findings, and Statement of Overriding Considerations (CEQA) to be considered by the SPRTA Board of Directors.  The Sutter County Board of Supervisions will separately consider formal adoption of the selected corridor within its jurisdiction based on the Final Tier 1 EIS/EIR.

    The Final Tier 1 EIS/EIR is expected to be completed by summer 2009. Corridor land acquisition can begin only after the Tier 1 EIS/EIR process is completed.

Federal Resource Agencies Coordination
The FHWA and PCTPA are committed to identifying and addressing environmental issues, including ones that could affect future federal permits required to construct the Parkway. So that these issues could be identified and satisfactorily dealt with during the Tier 1 review, FHWA, Caltrans, and PCTPA entered into an informal Memorandum of Understanding (Modified NEPA/404 MOU) with the U.S. Army Corps of Engineers (USACOE) and the U.S. Environmental Protection Agency (USEPA). The MOU modifies the NEPA/404 permitting process for wetlands and other “Waters of the U.S.” -- part of the U.S. Clean Water Act.

Although, the Placer Parkway Corridor Preservation project is not a construction project and does not require permits, the MOU outlines agreement to identify environmental issues that could affect future construction permit approvals. This process seeks to reach "concurrence" on the following:

  1. Purpose and Need Statement (Completed October 2005)
  2. Criteria for Selecting the Range of Alternatives (Completed October 2005)
  3. Range of Alternatives - general agreement reached – (Completed September 2006)
  4. Alternative(s) most likely to contain the Least Environmentally Damaging Practicable Alternative (LEDPA) (underway - to be completed before the final Tier 1 EIS/EIR is finished)
  5. Mitigation Strategy Framework (to be completed before the final Tier 1 EIS/EIR is finished)

The discussion on the Range of Alternatives focused on ways to avoid building a new transportation facility. A number of potential concepts were analyzed. Based on this work, the group concluded that no feasible corridor alternatives could be identified that did not involve a new roadway. It was further agreed that the five ‘build’ corridor alternatives (identified by the SPRTA Board) would be considered with a commitment to construction options and resource protection techniques as a way to meet avoidance obligations.

Placer County Conservation Plan (PCCP)
Placer County is pursuing a Natural Community Conservation Plan (NCCP) and Habitat Conservation Plan (HCP). It is referred to as the Placer County Conservation Plan (PCCP). Phase 1, for portions of the western County, would allow specific development projects to comply with several federal and State laws involving federal and State endangered/threatened species over the next 50 years.

Since 2004, SPRTA considered becoming a participating agency in the PCCP. In doing so, the Parkway would be a covered activity. The benefit of participating would be that the PCCP would identify all of the Parkway’s direct, indirect, and cumulative impacts and mitigation requirements related to the:

  • Federal Endangered Species Act
  • California Endangered Species Act
  • Natural Communities Conservation Planning Act
  • California Dept. of Fish and Game’s Stream Alteration Permit

This, in turn, would provide certainty and time savings in completing future Parkway Tier 2 environmental and construction requirements.

On December 7, 2005, the SPRTA Board approved an allocation not to exceed $155,000 as SPRTA’s contribution for PCCP preparation. This allocation is contingent upon completing an acceptable planning agreement with the County and resource agencies.

On January 23, 2007, the Placer County Board of Supervisors directed County staff to proceed with work associated with development of the PCCP.  The County requested staff participation from partner agencies - SPRTA and the Placer County Water Agency.

 


Project Description | Corridor Alternatives | Environmental Review | Funding | Public Outreach | Project Schedule | Project Library | Who to Contact

Placer County Transportation Planning Agency
299 Nevada Street  ● Auburn, CA 95603
(530) 823-4030 ● (530) 823-4036 - fax
email PCTPA