Public Outreach |
Month |
Technical Process |
| |
January |
Drafts submitted to
Caltrans:
- Air Quality
Technical Memorandum
- Traffic Noise
Analysis Technical Memorandum
- Public
Participation Methodology Report
|
|
February 2007 Newsletter |
February |
Caltrans accepted all
draft technical reports
1st Admin. Draft Tier 1
distributed for Caltrans review |
| |
March |
Project Development Team
Meeting #17
Caltrans submitted 1st Admin. Draft Tier 1 comments
|
|
Placer Co. Board of
Supervisor’s briefings |
April |
Caltrans completed 2nd
Admin. Draft comments |
| |
May |
MEPLAN Technical Report
FHWA Briefing: Draft Tier
1 EIS/EIR & technical reports
Sutter Co. Briefing:
Draft Tier 1 EIS/EIR & technical Reports
Admin. Draft: Interim
Report: Summary of Modified NEPA/404 Consultation
through Concurrence Point #3
FHWA & Sutter Co.
completed draft comments
Draft Engineering
Summary Report completed |
|
Notice
of Availability
Press
Release |
June |
Modified NEPA/404 Meeting #17
Notice of Completion (State Clearinghouse)
Draft Tier 1 EIS/EIR distributed for public comment &
review |
|
July 2007
Newsletter |
July |
Public comment period
begins |
|
SPRTA
Board Public Hearings to get comments on Draft Tier 1
EIS/EIR:
Yuba City - August 6
Roseville - August 8 |
August |
|
| |
September |
Public Comment Period
Closes |
|
Project
Update: Sun City Roseville, Community Relations
Committee |
October |
|
| |
November |
Modified NEPA/404 Meeting
#18 |
| |
December |
|